1.Agile team is developing a complex product in iteration. In the third iteration, the product owner found a problem. What should the product owner tell the team?
- A. Create a difficult spy story
- B. Continue adding features because the iteration has started
- C. Cancel and reschedule sprint
- D. Increase the sprint length because additional features have been added
敏捷團隊在迭代中,正開發一個復雜的產品。在第三次迭代中,產品負責人發現了一個問題。產品負責人應該告訴團隊什么?
- A、創建一個難點刺探故事
- B、繼續添加功能,因為迭代已開始
- C、取消并重新計劃 Sprint
- D、增加 Sprint 長度,因為添加了額外功能
2.The agile project team received an urgent request during the iteration. What should agile project managers do first?
- A. Stop working on the unfinished user story and work on the request first
- B. Call a team meeting to change the iteration scope to include the request
- C. Provide project team suggestions to customers
- D. Explain that the team cannot include the request until the next iteration
敏捷項目團隊在迭代期間收到一個緊急請求。敏捷項目經理首先應該做什么?
- A、停止未完成用戶故事的工作,先為該請求工作
- B、召開一場團隊會議,更改迭代范圍以包含該請求
- C、向客戶提供項目團隊建議的意見
- D、解釋到下一次迭代之前,團隊不能包含該請求
3.An external stakeholder wants to be informed of the risks and problems that are coming. What should scrum executives do?
- A. Meet with the external stakeholders to review the risk register
- B. Meet with the external stakeholders to review the project plan
- C. Regularly update the project plan and send it to external stakeholders for review
- D. Direct the external stakeholder to view the source of the information
一名外部干系人希望被告知即將發生的風險和問題。Scrum 主管應該怎么做?
- A、與該外部干系人會面,審查風險登記冊
- B、與該外部干系人會面,審查項目計劃
- C、定期更新項目計劃,并發送給外部干系人審查
- D、指引該外部干系人查看信息發射源