1.Three teams are currently on day 8 of a 2-week sprint. The team speed is 30, and 20 story points have been completed, but the team can only complete another 6 story points. How should the team solve the story point gap?
- A. Add extra tasks to the to-do that represent two story points
- B. Remove the lowest priority task that represents four or more story points from the to-do list
- C. Extend iteration length by two days
- D. Reduce iteration length by two days
有 3 個團隊目前正處于一個為期 2 周的 Sprint 的第 8 天。團隊速度為 30,有 20 個故事點已經完成,但團隊只能額外再完成 6 個故事點。團隊應如何解決故事點差距?
- A、在待辦事項中添加代表兩個故事點的額外任務
- B、從待辦事項中刪除代表四個或更多故事點的最低優先級任務
- C、延長迭代長度兩天時間
- D、減少迭代長度兩天時間
2.According to the figure below, what is the current state of the iteration when comparing the planned and completed story points?
- A. Iteration is in danger
- B. The team has deleted the scope
- C. Iteration ahead of schedule
- D. Team speed is stable
根據下圖,對比計劃的故事點和已完成的故事點時,迭代的當前狀態是什么?
- A、迭代處于危險之中
- B、團隊已經刪除范圍
- C、迭代提前于進度
- D、團隊速度穩定不變
3.Which of the following statements about epic stories is true?
- A. Epic stories need to be decomposed at the functional boundary
- B. Epic stories are not product specific
- C. Epic stories are user stories that can be completed in one iteration
- D. Epic stories can be broken down into smaller user stories
下列針對史詩故事的說法哪一項是正確的?
- A、史詩故事需要在功能邊界分解
- B、史詩故事并不代表產品特辦事項
- C、史詩故事是指可以在一次迭代中完成的用戶故事
- D、史詩故事可以分解成較小的用戶故事